CIP Trophy Club Drive

TCDMapThis project is for road construction on the following street(s):

  • Trophy Club Drive  (Southbound Side Only from Durango Drive to Bobcat Blvd)

This project road construction includes:

  • Pavement removal
  • Road reconstruction
  • Storm drain improvements
  • Waterline improvements

Project Updates

The Town staff intends to provide updates on the happenings as much as it is available. Please remember that the information provided is what is available to staff via their team and other third parties and it is subject to change. Staff will strive to keep Trophy Club looking and functioning at its best while keeping its residents informed to the best of their abilities.

November 12, 2019:

A sign was added to the existing stop sign at Trophy Club Drive and Bobcat today that informs drivers that cross traffic doesn’t stop.  The goal is to inform those turning South on Trophy Club Drive that the intersection is not a four-way stop and that they should yield to the through traffic. Staff hopes this will provide more direction and clarity to drivers at this particular intersection.

November 08, 2019:

The town notified the Meadow Ridge HOA earlier in the week that the trees along Trophy Club Drive would need to be trimmed to a canopy height of 15 ft. Equipment required for the construction could not do the work unless the canopy was raised.  These trimmings took place and though seem unsightly were necessary for work to continue on the CIP project.

November 02, 2019: (UPDATE)

Last night’s experience with the road closure in place, was like many. It can look good on paper, but the test is putting it to the task. Staff worked this morning to correct some areas of concern and will continue monitoring activity even when it has become smooth.

Pavement removal, originally scheduled for the week of December 2nd, will now begin the week of November 4th. The contractor has done a great job in the first of three(3) phases and is now ahead of schedule.

For questions, please contact Tommy Uzee at 682.237.2915 or TUzee@trophyclub.org

TC Drive 2

November 02, 2019:

Following three accidents at Durango and Trophy Club Drive during the evening of Oct 31, the following modifications were made immediately in the morning to help traffic flow as smoothly as possible:

  • Widening the turn Southbound as well as to add a gradual merge lane South. 
  • Crews made adjustments at Bobcat and Trophy Club Drive so turns could be wider and easier for vehicles and larger transpo, such as school buses, to make their maneuvers safely.  

After these changes were made, Director Uzee spoke with the contractor and found out that some of the traffic issues which caused backups were the result of heavy equipment deliveries for the project.  Director Uzee requested moving forward that any deliveries of the like be done in off-peak hours to help avoid backups with traffic.  

These proactive adjustments are a direct example of our team doing as they promised in monitoring the situation and making necessary and appropriate adjustments!

November 01, 2019:

TC Drive CONSTRUCTION: This morning, Trophy Club Police Department  is working with the Streets Division and the Project Contractor to make adjustments and changes for the current traffic flow on Trophy Club Drive and Durango.  If you’re turning SOUTHBOUND from Durango Drive onto Trophy Club Drive, the NEW traffic flow will now allow you to turn South onto Trophy Club Dr. and merge down by the apartments.

October 30, 2019:

Town Hall meeting was held on October 30, 2019.  Watch the video HERE.


Construction will BEGIN OCTOBER 31, 2019.  If you have any questions, please contact Tommy Uzee at TUzee@trophyclub.org or 682.237.2915

October 24, 2019:

The Town of Trophy Club will be hosting a Town Hall Meeting on Wednesday, October 30, 2019, at 6:00 PM in the Town Hall located at 1 Trophy Wood Drive. 

The purpose of this meeting is to offer an opportunity for residents to inquire about the Capital Improvement Projects (CIP) on Trophy Club Drive which is about to begin. The road reconstruction project includes pavement removal, storm drain improvements, water line improvements, and sidewalk installations. Representatives from Teague Nall & Perkins, Jackson Construction and NISD will be in attendance.  We hope to see you at the meeting.

Town Hall Meeting Notice Oct Opens in new window

October 23, 2019:

Below are images from the Trophy Club Drive Closure document provided by the contractor.  These images are for illustrative purposes only and are not intended to relieve the contractor from their contract documents.   

S4-3 3237 TROPHY CLUB CLOSURE revised-1 Opens in new window

S4-3 3237 TROPHY CLUB CLOSURE revised-2 Opens in new window

S4-3 3237 TROPHY CLUB CLOSURE revised-3 Opens in new window

S4-3 3237 TROPHY CLUB CLOSURE revised-4 Opens in new window

October 14, 2019:

Sundance Court is wrapping up construction three weeks ahead of schedule which means attention will now shift to Trophy Club Drive.  Here are the nuts and bolts of what to expect during this phase of construction.

  • Contractors will be mobilizing onto Trophy Club Drive beginning October 21.
  • Detour signs will be placed during the week of the 27.
  • Trophy Club Drive will have all concrete replaced between the curbs (west side to the island) on the southbound lane.
  • Two-way traffic will be on the northbound lane during construction, between Bobcat Boulevard and Durango Drive.
  • A left turn lane from Trophy Club Drive will be added to the northbound lanes for access to Durango Drive.
  • Construction is scheduled for completion by May 11, 2020.

TCDMap

July 10, 2019

Town Hall Meeting held for the public to further explain project details, answer questions from the contractor and receive an anticipated schedule of activities.  Estimated project start date (Sundance Court) is July 22, 2019.
Town Hall Meeting Notice

June 28, 2019 - 2:00 PM

Precon meeting held between Town staff, Teague, Nall & Perkins (TNP) and Jackson Construction in which details and plans were reviewed and discussed.  Town Hall Meeting scheduled for July 10, 2019 at 7:00 PM for residents to hear from contractors and ask questions.  The sequence of construction at this time will take place with the following estimates in timing from the date of section start:

  • Sundance Court
         - Estimated substantial completion within 90 calendar days
         - Estimated final acceptance within 15 calendar days
  • Trophy Club Drive
         - Estimated substantial completion within 160 calendar days
         - Estimated final acceptance within 30 calendar days
  • Meadowbrook Lane
         - Estimated substantial completion within 100 calendar days
         - Estimated final acceptance within 15 calendar days

May 14, 2019 - 8:00 PM

Town Council approved a contract with Jackson Construction for work with the anticipated project start date of July 22, 2019.  The project will start with Sundance Court, followed by Trophy Club Drive, then Meadowbrook Lane.

April 17, 2019 - 1:00 PM

The latest schedule for the Trophy Club Drive, Sundance Court, and Meadowbrook Lane road construction has been accepted. The project is scheduled for commencement on June 3, 2019, and will begin with Sundance Court. This will prevent any confusion with the July 4, 2019 parade. Trophy Club Drive will commence on, or about, July 8, 2019.