We are at the final stage of the Indian Creek Project. At this time, approximately 80% of the project is complete. The installation of the headwall & rock rip-rap in the back by the golf course began this week. This will also include abandoning the 48" pipe (between 22 and 20 Fair Green). This will take about two weeks.
The landscape & irrigation restoration has also begun this week (which includes the four residential homes between Fair Green and Indian Creek). Restoration cannot begin between Fair Green and the golf course until access is no longer needed. The headwall and rock rip-rap are on the golf course property, and access is between 22 and 20 Fair Green. The estimated substantial completion (95%) date is 8/26/2022.
We apologize for the inconvenience and appreciate your patience during this work. If you have any questions, please contact us at info@trophyclub.org.